Monday, 22 December 2014
Home

13.gif

Visitor Hits




   12 online
EINRIP Loan Amendment No. 3
Friday, 12 December 2014

Following upon the discussion at Joint Management Meeting between Government of Indonesia and Government of Australia held in April 2014, the EINRIP Loan AIPRD L-002 has now been extended to a new Closing Date of 30 September 2015, from the current Loan Closing Date of 31 December 2014.

The Amendment No. 3 to the Project Loan Agreement was signed on 25 November 2014. The loan has now been extended to 30 September 2015 and the loan amount remains unchanged at AUD 300 million.

 

 

See amendment no. 3 to the Project Agreement.


 

 
Project Progress Report October 2014
Friday, 28 November 2014

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 Loan Agreement for Eastern Indonesia National Road Improvement Project (EINRIP), the monthly Project Progress Report (PPR) for month of October 2014 is now available. Summary provided in the report are:

Loan Agreement - The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement, signed on 28 February 2013. Currently, a proposed third extension to loan closing date to 30 September 2015 is under discussion and under process.

Environmental Studies and Land Acquisition - From the  20 packages included under EINRIP, environmental studies required for all 14 packages were complete by end of 2010, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi. There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.

Procurement of Civil Works - Procurement for all 20 Civil Works packages was complete at end of November 2012.

Variation Orders (V.O.) - During October 2014, NOLs were issued by Australian Aid for V. O. No. 2 for package ESS-05, V. O. No. 2 for ESS-06, V. O. No. 5 & 6 for ENT-01, V. O. No. 4 for ESH-01 and Contract Amendment No. 7 & 8 for ESK-02.

Project Financial Status (31 October 2014) - Cumulative advances to Special Account to date: A$ 263.81 million, Balance in Special Account on 31 October 2014 : A$ 9.85 million and Expenditure charged to Special Account during October 2014 : A$ 5.12 million.

Other Matters

HIV/AIDS Prevention Campaign for ESS-06 (27-31 October, 2014) was conducted by RSC.

Submission of Financial Monitoring Report (FMR) No. 24 period July - September 2014 on 23-Oct-2014.

 

 

 

 

Full report clik here …



 

 
Financial Monitoring Report No. 24 July - September 2014
Thursday, 30 October 2014

Explanation of FMR No. 24 (period July - September 2014) as follows :

Up to 3rd Quarter 2014, the cumulative expenditure is Rp 2,600.75 billion (AUS$ 277.96 million) with sources of funds as follow:

  • GOA (Australian Aid)  : Rp. 2,318.62 billion (AUS$ 247.86 million).
  • GOI Counterpart       : Rp.    282.13 billion (AUS$   30.10 million).

And the detail uses of funds by category up to 3rd Quarter 2014 are as follow:

 

NoCategoryPayments GOAPayments GOI
(In Million)(In Million)
Q3- 2014Cumulative to DateQ3 - 2014Cumulative to Date
IDRAUDIDRAUDIDRAUDIDRAUD
1 Civil Works 41,911.41 3.887 2,029,543.15 215.887 5,698.07 0.528 275,925.03 29.351
2 Goods 0.00 0.000 40,882.96 5.006 0.00 0.000 5,558.25 0.677
3 IOC 528.90 0.049 5,109.42 0.575 67.44 0.006 648.15 0.073
4 Implementation Support 14,114.19 1.300 243,088.78 26.393 0.00 0.000 0.00 0.000
Total 56,554.50 5.237 2,318,624.31 247.862 5,765.51 0.535 282,131.42 30.101

 

3rd Quarter 2014 shows total of expenditure is Rp. 62.32 billion (AUS$ 5.77 million) with sources of funds as
follow:

  • GOA (Australian Aid) : Rp. 56.55 billion (AUS$ 5.24 million)
  • GOI Counterpart      : Rp.   5.76 billion (AUS$ 0.53 million)

And the detail uses of funds by category in 3rd Quarter 2014 are as follows.....

 

 

See detail


 
Project Progress Report September 2014
Wednesday, 29 October 2014

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 Loan Agreement for Eastern Indonesia National Road Improvement Project (EINRIP), the monthly Project Progress Report (PPR) for month of September 2014 is now available. Summary provided in the report are:

Loan Agreement - The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement, signed on 28 February 2013. Currently, a proposed third extension to loan closing date to 30 September 2015 is under discussion and under process.

Environmental Studies and Land Acquisition - From the  20 packages included under EINRIP, environmental studies required for all 14 packages were complete by end of 2010, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi. There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.

Procurement of Civil Works - Procurement for all 20 Civil Works packages was complete at end of November 2012.

Variation Orders (V.O.) - During September 2014, NOLs were issued by Australian Aid for V.O. No. 04 EKS-01 and V.O. No. 07 ESS-01.

Project Financial Status (30 September 2014) - Cumulative advances to Special Account to date: A$ 263.81 million, Balance in Special Account on 31 September 2014 : A$ 14.96 million and Expenditure charged to Special Account during September 2014 : A$ 2.65 million.

Other matters - HIV/AIDS Prevention Campaign for ENT-01 (7-13 September, 2014) was done by RSC. The 2nd Road Safety Audit was carried out on site for ESS-05 (31 August – 1 September 2014) and ESS-06 (1-2 September 2014).  Report was issued by Australian Aid on 23 September 2014.

 

 


 
1234

   

| Site Map | Contact Us | About Us | FAQs |