|
In accordance with clause III.A.1(a) of Schedule 2 of AIPRD-L002 loan agreement for Eastern Indonesia National Road Improvement Project (EINRIP), this is the monthly Project Progress Report (PPR) for March 2012.
Loan Agreement
The original loan closing date of 1 June 2011 has been extended to 31 March 2013 and amendment to the Loan Agreement was signed on 9 June 2011.
Environmental Studies
From the 20 packages now included under EINRIP:
• Environmental studies were not required for 6 packages.
• Environmental studies (UKL/UPL) for 11 packages have been completed.
• AMDAL for ESS-04, ESS-05 and ESS-06 is complete, approval granted by Governor of South Sulawesi.
Land Acquisition
Of the 20 packages now included under EINRIP:
• There was no land acquisition required for 2 packages.
• Land acquisition for 16 packages is complete.
• Compensation payments for land acquisition in packages ESS-05 & ESS-06 (LG Bulukumba and Sinjai in South Sulawesi) commenced in late 2011 and are ongoing.
Procurement of Civil Works
• Procurement completed for 18 packages and contracts have already commenced construction.
• Procurement process for two packages ESS-05 and ESS-06 commenced in July 2011 and bid opening was held in Makassar on 22-Nov 2011.
• The BER for both packages has been completed and submitted to AusAID. Additional clarifications were asked from the bidders, and revised BER was sent to AusAID in Feb-2012. NOL for Award for both packages was issued by AusAID on 29 February 2012.
• The Notification of Awards for both packages was issued on 16 March 2012.
• Successful bidder for ESS-05 is PT Multi Structure (Bid Price Rp 97.536 billion); and for ESS-06 is PT Waskita Karya (Bid Price Rp 126.750 billion).
|