Saturday, 29 August 2015
Home

5.gif

Visitor Hits




   329 online
Project Progress Report June 2015
Friday, 31 July 2015

In accordance with clause III.A (a) of Schedule 2 of AIPRD-L002 loan agreement for Eastern Indonesia Natioanal Road Improvement Project (EINRIP),

this is the monthly Project Progress Report (PPR) for June 2015.

The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No.2 to the Project Loan

Agreement, signed on 28 February 2013.

The Amendment No.3 to the Project Loan Agreement which was formally signed on 25 November 2014 has extended the Loan Closing date to 30

September 2015. The Loan Amendment No.3 includes re-allocation of funds within existing categories, while the total loan amount remains unchanged

at A$300 million.


Environmental Studies and Land Acquisition

  • Of the 20 package included under EINRIP, environmental studies required for all 14 packages were complete by end of 2010, including

the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi.

  • There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.

 

 

 

 

Full Report Click Here .......

 
Financial Monitoring Report No.27 For Period April-June 2015
Friday, 31 July 2015

Explanation of FMR No.27(period April - June 2015) as follows:

 

Up to 2ndQuarter 2015, the cumulative expenditure is Rp.2.862.402billion (AUS$303.315million) with sources of fund as follow:

 

- GOA (Australian Aid)       Rp. 2,554.355billion (AUS$270.694 million)

- GOA Countepart              Rp. 308.047 billion (AUS$32.621 million)

 

And the detail uses of funds by categoy up to 2ndQuarter 2015 are as follow


No

Category

Payments GOA

Payments GOI

(In Million)

(In Million)

Q2 - 2015

Cumulative to Date

Q2 - 2015

Cumulative to Date

IDR

AUD

IDR

AUD

IDR

AUD

IDR

AUD

1

Civil Works

36,285.60

3.542

2,219,932.43

234.404

4,933.21

0.481

301,810.21

31.868

2

Goods

0.00

0.000

40,882.96

5.006

0.00

0.000

5,558.25

0.677

3

IOC

174.78

0.017

5,341.76

0.598

23.12

0.002

678.59

0.076

4

Implementation Support

9,235.97

0.912

288,197.71

30.686

0.00

0.000

0.00

0.000

Total

45,696.35

4.471

2,554,354.86

270.694

4,956.33

0.484

308,047.05

32.621

 

2ndQuarter 2015 shows total of expenditure is Rp.50.653 billion (AUS$4.955 million) with sources of funds as follow:

 

- GOA (Australian AID)          : Rp.45.696 billion (AUS$4.955 million) with sources of funds as follow:

- GOA Counterpart                : Rp. 4.956 billion (AUS$0.484 million)

 

And the detail uses of funds by category in 2ndQuarter 2015 are follows:

 

2ndQuarter 2015 shows total of expenditure is Rp. 50.653 billion (AUS$4.955million) with so

 

Full Report Click here....

 

 

 
Project Progress Report May 2015
Wednesday, 01 July 2015

 

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 loan agreement for Eastern Indonesia National Road Improvement Project (EINRIP), this is the monthly Project Progress Report (PPR) for May 2015.

Loan Agreement

The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement, signed on 28 February 2013.

The Amendment No. 3 to the Project Loan Agreement which was formally signed on 25 November 2014 has extended the Loan Closing date to 30 September 2015. The Loan Amendment No. 3 includes re-allocation of funds within existing categories, while the total loan amount remains unchanged at A $300 million.

Environmental Studies and Land Acquisition

  • Of the 20 packages included under EINRIP, environmental studies required for all 14 packages were complete by end of 2010, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi.
  • There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.

Procurement of Civil Works

Procurement for all 20 Civil Works packages was complete at end of November 2012.

Variation Orders (V.O.)

During May 2015, NOL was issued by DFAT for V. O. No. 4 for ESS-05, V. O. No. 7 for ENT-01 and V. O. No. 4 & 5 for ENB-01AB.

Project Financial Status (31 May 2015)

  • Cumulative advances to Special Account to date: A$ 290.024 million.
  • Balance in Special Account on 31 May 2015: A$ 20.743 million.
  • Expenditure charged to Special Account during May 2015: A$ 1.715 million.

Others

  1. The M&E Consultant of DFAT presented the findings and preliminary economic analysis of 2014 M& Surveys in DGH on 12 May 2015.
  2. Meeting was held in DGH, Jakarta, on 18-May 2015 for discussion on acceleration and completion of Works on package ESS-05 (Bulukumba-Tondong).
  3. On 18-20 May, 2015, a team from Bappenas undertook a Monitoring Visit to Bali, of EBL-01 and EBL-02 (Tohpati-Kusamba) as part of evaluation of EINRIP project.

 

Full Report Click Here ...


 

 
Project Progress Report April 2015
Wednesday, 27 May 2015

 

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 Loan Agreement for Eastern Indonesia National Road Improvement Project (EINRIP), the monthly Project Progress Report (PPR) for month of November 2014 is now available. Summary provided in the report are:

Loan Agreement - The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement, signed on 28 February 2013. The Amendment No. 3 to the Project Loan Agreement which was formally signed on 25 November 2014 has extended the Loan Closing date to 30 September 2015. The Loan Amendment No. 3 includes re-allocation of funds within existing categories, while the total loan amount remains unchanged at A$ 300 million.

Environmental Studies and Land Acquisition - From the 20 packages included under EINRIP, environmental studies required for all 14 packages were complete by end of 2010, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi. There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.

Procurement of Civil Works - Procurement for all 20 Civil Works packages was complete at end of November 2012.

Variation Orders (V.O.) - During November 2014, NOL was issued by DFAT for V. O. No. 5 for ESH-01.

Project Financial Status (30 November 2014)  - Cumulative advances to Special Account to date: A$ 263.81 million, Balance in Special Account on 30 November 2014 : A$ 8.66 million and Expenditure charged to Special Account during November 2014 : A$ 1.30 million.

Other Matters A meeting was held with Staff of Kabupaten Sumbawa (NTB) on progress of EINRIP Land Certification Program in Kabupaten Sumbawa for Packages ENB-01 AB, ENB-01C and ENB-02 on 13 November 2014.


 

Full Report Click Here ...


 

 
12345678

   

| Site Map | Contact Us | About Us | FAQs |