Sunday, 31 August 2014
Home

9.gif

Visitor Hits




   11 online
Project Progress Report July 2014
Wednesday, 27 August 2014

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 Loan Agreement for Eastern Indonesia National Road Improvement Project (EINRIP), the monthly Project Progress Report (PPR) for month of July 2014 is now available. Summary provided in the report are:

Loan Agreement - The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement that was signed on 28 February 2013. Currently, a third extension to loan closing date to September 2015 is being processed.
Environmental Studies - From the 20 packages now included under EINRIP, environmental studies required for all 14 packages is complete, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi.
Land Acquisition - There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.
Procurement of Civil Works - Procurement for all 20 Civil Works packages was complete at end of November 2012.
Variation Orders (V.O.) - During July 2014, no NOL was issued by Australian Aid.
Project Financial Status (31 July 2014) - Cumulative advances to Special Account to date: A$ 261.95 million, Balance in Special Account on 31 July 2014 : A$ 17.23 million and Expenditure charged to Special Account during July 2014 : A$ 0.77 million

 

Full report click here…..

 


 

 

 
Project Progress Report June 2014
Friday, 08 August 2014

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 Loan Agreement for Eastern Indonesia National Road Improvement Project (EINRIP), the monthly Project Progress Report (PPR) for month of June 2014 is now available. Summary provided in the report are:

Loan Agreement - The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement that was signed on 28 February 2013.

Environmental StudiesFrom the 20 packages now included under EINRIP, environmental studies required for all 14 packages is complete, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi.

Land AcquisitionThere was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.

Procurement of Civil WorksProcurement for all 20 Civil Works packages was complete at end of November 2012.

Variation Orders (V.O.)During June 2014, NOL was issued by Australian Aid for V. O. No. 9 for ESU-01.

Project Financial Status (30 June 2014) - Cumulative advances to Special Account to date: A$ 261.95 million, Balance in Special Account on 30 June 2014 : A$ 17.20 million and Expenditure charged to Special Account during June 2014 : A$ 3.56 million.

 

Full report click here…


 

 
Financial Monitoring Report No.23 For Period April - June 2014
Monday, 21 July 2014

Explanation of FMR No. 23 (Period April - June 2014) as follows :

Up to 2nd Quarter 2014, the cumulative expenditure is Rp 2,538.43 billion (AUS$ 272.19 million) with sources of funds as follow:

  • GOA (Australian Aid) : Rp. 2,262.07 billion (AUS$ 242.62 million).
  • GOI Counterpart : Rp. 276.36 billion (AUS$ 29.57 million).

And the detail uses of funds by category up to 2nd Quarter 2014 are as follow:

 

NoCategoryPayments GOAPayments GOI
(In Million)(In Million)
Q2- 2014Cumulative to DateQ2 - 2014Cumulative to Date
IDRAUDIDRAUDIDRAUDIDRAUD
1 Civil Works 57,414.67 5.251 1,987,631.74 212.000 7,805.81 0.714 270,226.96 28.822
2 Goods 0.00 0.000 40,882.96 5.006 0.00 0.000 5,558.25 0.677
3 IOC 0.00 0.000 4,580.52 0.526 0.00 0.000 580.71 0.067
4 Implementation Support 0.00 0.000 228,974.59 25.093 0.00 0.000 0.00 0.000
Total 57,414.67 5.251 2,262,069.81 242.625 7,805.81 0.714 276,365.91 29.566

 

2nd Quarter 2014 shows total of expenditure is Rp. 65.22 billion (AUS$ 5.96 million) with sources of funds as
follow:

  • GOA (Australian Aid) : Rp. 57.41 billion (AUS$ 5.25 million)
  • GOI Counterpart : Rp. 7.81 billion (AUS$ 0.71 million)

And the detail uses of funds by category in 2nd Quarter 2014 are as follows.....

 

 

See detail


 
Project Progress Report May 2014
Tuesday, 01 July 2014

In accordance with clause III.A.1 (a) of Schedule 2 of AIPRD-L002 Loan Agreement for Eastern Indonesia National Road Improvement Project (EINRIP), the monthly Project Progress Report (PPR) for month of May 2014 is now available. Summary provided in the report are:

Loan Agreement - The original loan closing date of 1 June 2011 was extended to 31 December 2014, (2nd extension) through the Amendment No. 2 to the Project Loan Agreement that was signed on 28 February 2013.
Environmental Studies - From the 20 packages now included under EINRIP, environmental studies required for all 14 packages is complete, including the AMDAL for ESS-04, ESS-05 and ESS-06 in South Sulawesi.
Land Acquisition - There was no land acquisition required for 2 packages. Land acquisition for 18 packages is complete.
Procurement of Civil Works - Procurement for all 20 Civil Works packages was complete at end of November 2012.
Variation Orders (V.O.) - During May 2014, NOL was issued by Australian Aid for Price Adjustment for package ENB-03.
Project Financial Status (31 May 2014) Cumulative advances to Special Account to date: A$ 261.95 million, Balance in Special Account on 31 May 2014: A$ 21.57 million and Expenditure charged to Special Account during May 2014 : A$ 1.64 million

 

Full report click here…


 

 
123

   

| Site Map | Contact Us | About Us | FAQs |